Central Bank Strives to mordernise
Payments System in Lesotho
The Central Bank
of Lesotho is in the process of reviewing commonly used
payment methods by individuals and businesses with the
intention of introducing a modernised payment system.. This
process comes in the wake of a realisation that current
payment practices are slow, costly and unsafe.
Limitations of
Traditional Method of Payment
It has been
realised that the current methods of payment have various
shortcomings such as inordinate delays, high costs, and the
risk of fraud. The most common instruments that
characterise these payment methods are cash, cheques, and to
a limited extent electronic payments.
Cash payments are
only convenient and easy to use for small, one-on-one or
point-of-sale transactions. Since carrying cash around is
risky, most large transactions are paid for by cheques or
through electronic mechanisms. Although paper-based
payments or cheques reduce the risk of theft, their major
drawback is that they are processed manually particularly in
countries that are less technologically advanced. This
makes them labour intensive and thus prone to errors. As a
result, cheque payments tend to increase the time lag
between when payment for goods and services is made and the
time the supplier actually receives the value for goods or
services provided. This delay is referred to as the
settlement period. At one time, settlement period in
Lesotho was as high as 21 days. In more developed countries
same-day settlement is commonplace. This means that Lesotho
has a long way to go in reducing settlement period.
Objectives of Modernising the Payment System
The major focus of the Central Bank is to improve the
payment system in Lesotho with particular emphasis to
reducing settlement period. In this new system, it is
envisaged that the costs of making payments will also be
reduced. The Bank also intends to meet international
standards in terms of providing secure means of making
payments. Some of the distinguishing factors of the
traditional method of payment and the proposed modernised
system are captioned as below:
|
Traditional Method of Payment |
Modernised System
|
|
1.Speed |
1. Speed |
|
Settlement
period of up to 21 days. |
Same-day
settlement |
|
2. Certainty |
2.
Certainty |
|
Uncertainty of
sufficient funds in the Account, particularly in cheque
transactions |
Funds are
immediately and irrevocably available |
|
3.
Reliability |
3. Reliability |
|
Payment
process is stalled if there is fault. |
The system
possesses adequate contingency provisions and controls
in case of fault |
|
4. Safety
and Security |
4. Safety
and Security |
|
Lack of fraud
control |
The system
ensures against unauthorised access (fraud) |
In an effort to
transform the traditional payment system into the modernised
one that will conform to the international standards, the
Bank set up the Lesotho National Payment System
Modernisation Project, which was launched in 1999. A
project manager was employed as from 1st August
2000 to work on the project on a full-time basis. The aim
was to review the current payment system, to analyse the
current and future payment needs and requirements of all
population and the economy, and to review, upgrade and
improve systems that are currently in operation.
Lesotho
Businesses and Individuals to Benefit from the New System
All players in the
economy are set to benefit from the improved system. For
one thing suppliers will get value for their services within
two days even if payment is done by cheque. Secondly, the
need to carry large amounts of cash, with the attendant
risks of theft will be reduced. Lesotho businessmen wishing
to procure goods from South Africa will no longer have to
carry cash with them as cross-border payments will be just
as efficient and cost effective as payments in South-Africa.
What has been done
so far
In its quest to
make headway for the implementation of this new system, the
Central Bank has already made a significant progress. The
Clearing System between Banks and branches in Lesotho was
reviewed and changes that reduced the settlement periods
from up to 21 days to a maximum of 3 days were implemented.
Secondly, a computerised clearing system was introduced at
the Central Bank with the objective of streamlining the
procedures and eliminating a number of manual processes.
Lastly, an Agency Agreement and Clearing House Rules between
commercial banks in Lesotho were developed and signed on the
25th October 2000. The purpose of this agreement
is to create uniform rules and regulations within which
banks must act, and to set mutually agreed time frame within
which certain actions must be finalised, for instance,
dishonour of cheques.
The foregoing
activities constitute Phase I of the Payment System
Modernisation Project. Efforts are now underway in regard
to achieving the objectives of Phase II that will deal with
ways of further enhancing the functionality and speed of the
domestic payment arrangements, including the use of
electronic payments methods. Phase II is envisaged to
concentrate on cross-border settlement arrangements which
will be pursued in tandem with SADC Payment System Project.
The stocktaking
and situational analysis was completed in 2003, and it
indicated the need for the reform of the payment system.
Based on the results, a vision was formulated and was
adopted by the Lesotho National Payment System Council . The
latter is composed of the Governor, the Chief Executive
Officers of Commercial Banks, Telecommunications and Energy
Industries, and the Principal Secretary for the Ministry of
Finance and Economic Planning. The vision states that "By
2015, Lesotho will have a widely accessible, secure,
reliable and efficient payment and settlement system. the
system shall facilitate and support Lesotho's development
objectives."
So far a draft
strategic framework has been prepared. It has identified ;
- future
characteristics of the new payment system
- critical success
factors against which the successful implementation of the
reform process would be measured and
- the fundamental
principles that will guide the development, deployment and
management of the new system.
DEVELOPMENTS IN
2002
ORGANISATIONAL
STRUCTURES
In August 2002 the Head of
National Payment System Division was engaged to set up the
Division and coordinate the activities of the Lesotho
National Payment system Modernisation Project, with the
assistance of the consultant Project Manager.
The organizational structure of
the LNPS Project was strengthened with the set up of
Sub-Committees made up of experts relevant to a payment
system. These sub-committees are for Audit, Legal, Public
Relations, Risk Management, and Information Technology and
Infrastructure. These sub-committees were intended to assist
the Steering committee in the payment system reform process.
Monthly meetings of the LNPS
Steering Committee and Sub-Committees were revived and held
throughout the year, to mainly assess progress on the work
programme on assigned duties.
WORK PROGRAMME
Towards the end of
2002 a rather ambitious work programme was formulated by the
Steering Committee and Sub-Committees, for the year 2003,
the highlights and of which were to:
1.
To
finalise the stocktaking and situational analysis exercise
by March 2003
2.
To
develop a vision and strategic framework document by June
2003
3.
To
complete the business and technical specifications for the
required system by August 2003 and to commence the
implementation of strategies to attain the envisaged payment
system.
FRAUD
AWARENESS SEMINAR
In February 2002,
a fraud awareness seminar was held for the local community
to sensitise them on fraudulent activities.
DEVELOPMENTS
IN 2003
STOCKTAKING
AND SITUATIONAL ANALYSIS
Information
gathering and stocktaking was a joint effort by all
committees of the LNPS project, with the sub-committees
assigned specific tasks. The head of National Payment System
division was assigned the task of information gathering by
way of questionnaires filled in by commercial banks, and the
receiving and coordination of reports from different
sub-committees. The exercise was finally completed.
The results of
the stock-take indicated the strengths and weaknesses of the
current payment system. The main shortcomings observed were
the rudimentary nature of the payment system infrastructure,
especially in the rural areas, the narrow payment
instruments base resulting in the dominance of cash and
cheque usage, very limited automation in the payment
processes, the limited number of financial intermediation in
Lesotho, dominance of paper-based payment instruments and
their manual processing, and the absence of a large value
transfer system.
VISION
STATEMENT
Based on the
results of the stocktaking and situational analysis, a
vision of the envisaged payment system was adopted which
stated as follows: “By 2015, Lesotho will have a widely
accessible, secure, reliable and efficient payment and
settlement system. The system shall facilitate and support
Lesotho’s development objectives”. The vision document
outlined the main objectives of the reform process, which
included putting in place an appropriate legal and
regulatory framework, a technological infrastructure such as
the RTGS system for management of settlement and other
risks, facilitation of cross-border trade, harmonisation of
the Lesotho payment system with international and regional
systems, broadening Lesotho’s money and capital markets by
way of introducing a payment system for handling large-value
and time-critical payment instructions and
delivery-versus-payment (DVP) for securities transactions,
and drastically reducing the use of cash and ensuring that
by 2015 eighty percent Lesotho households would have access
to basic payment services within a 10 km radius of their
homestead.
WAY FORWARD
Towards the end of
the year, it was decided that in order to attain this
envisaged payment system, it was necessary to engage
consultants who were specialists in the payment system
reform; especially in the SADC region to assist the Central
Bank and other LNPS project committee members.
Policy issues were
agreed beforehand which included the access criteria into
the clearinghouse, settlement system and payment
instructions transfers; the ownership and operator of the
clearinghouse; and the funding of the clearing system and
the settlement system.
DEVELOPMENTS IN
2004
Bankserv
consultants were engaged to undertake the business analysis,
conceptual design and business specifications of the new
payment system. This assignment would be carried as joint
venture between Bankserv, AST and Perago.
The project scope
consisted of the conceptual design, formulation of
strategies to align the current system with the one
envisaged, breaking down the conceptual design into business
specifications, and converting strategies into individual
projects.
The project start
date was 21 July 2004 and is expected to take 90 days. The
methodology followed is by way of workshops and participants
are from the commercial, the central bank, the Treasury
department, Minim telecommunications, energy and other
stakeholders. |